CENTRAL HEBER WATER & SEWER
REPLACEMENT PROJECT



Note: Utility connections and piping from the water meter/sewer clean out through your property ROW remains "Property Owner" Responsibility. < Click to See Examples >

-
Crews will enter your street and begin installation of items in the following order...
-
Water main line
-
Sewer main line
-
Pipeline laterals into properties for both water/sewer
-
Pressurized irrigation with laterals into properties
-
Fiber Optic Cable installation as identified by Strata Networks
-
Full Roadway paving to be completed
-
​
​
-
Access to property entry/exit points may be limited at times. Please contact hotline for assistance. Crews will be available onsite to accommodate if necessary.
-
Be prepared for occaisional roadway closures even for local traffic. Please use caution and follow posted detours. Contact hotline for issues or special needs regarding local access.