

CENTRAL HEBER WATER & SEWER
REPLACEMENT PROJECT

Updated 04/02/25 at 4:30 pm
LATEST NOTICES (est. work schedule):
-
Starting at 7:00 AM on Tuesday, April 1, through 7:00 AM on Monday, April 6, the intersection of 550 E and 500 N will be closed to all traffic. Please follow the posted detour signs to safely navigate around the area.
-
Additionally, due to inclement weather, the water service shutdown has been rescheduled to Thursday, April 3: 10:00 AM – 9:00 PM in multiple areas on the west side of Heber
-
As of March 26, up to seven crews are working at various locations (see map below)
-
Road asphalt restoration is anticipated by early May in affected areas
-
Within the next month, crews may begin work between 200 N and 300 N; however, pavement restoration in this area is scheduled for mid-to-late summer 2025.
-
Please avoid streets marked "Local Traffic Only" as asphalt has been removed, and parking is prohibited.
Image: Crews Paving as part of Phase 1B-2| 06/11/24
.jpg)
Image: Sewer/Water Excavation near 300 S and Main | 10/16/2024
UPDATED WORK LOCATIONS
| Through April 04, 2025 |
Construction Phase 1C Detour Map

* Schedule subject to change based on weather and material delivery
.jpg)
_edite.jpg)

Pressurized Irrigation (PI) is anticipated to resume starting mid-April, 2025. Exact dates are determined by the central water conservancy district. As a note, open ditch water typically begins flowing by the first week in May. If you have a new PI pipeline installed as a result of our project, you will need to apply for a permit to gain service. Please fill out a form below and turn it into the Heber Public City Works office @ 749 W 300 S,
Heber City, UT 84032
-
Work will continue along 300 N installing sewer and water main pipelines. Once completed, crews will return to replace service lateral connections will also to the water meter or cleanout. Pressurized Irrigation lines will continue to be the final major utility installed, along with fiber-optic cable in prescribed locations.
-
All excavated roads will be pulverized and repaved with new asphalt by the end of the summer. The paving schedule is as follows:
-
Mid-April: 400 N and north/south roads up to 300 N
-
July: 300 N and north/south roads up to 200 N
-
Late Summer: 200 N and north/south roads to 100N
-
PROJECT DESCRIPTION
The city's water and sewer infrastructure in the Central Heber area has significantly exceeded its service life. As such, necessary improvements essential to maintaining a safe and reliable water/sewer system for residents and businesses. The main focus for Phase 1 of the replacement program includes the East side of Main Street within the Central Heber area, as well as a four block stretch of sewer replacement along 3rd West.
Construction Days / Times
-
Daylight Hours
-
Mon - Fri
-
Sat-Sun (only as necessary)
-
No holidays
Contact Public Information



Info Hotline: (435) 406-4910
(Press 1 for live assistance)





Water Disconnect Notice(s):
Be prepared for planned water disconnections within active construction zones. You will receive 24-48 hr. notice. Water outages should last from approximately 9am to 6pm.
Landscaping Restoration:

Any outstanding Surface Restoration regarding phase 1B-1 (construction done in late 2023 and early 2024) is currently underway. Full restoration of property surface vegetation along the 300 S trail alignment has been completed. Emergent repairs to irrigation lines will be addressed on request. If you have immediate needs, contact our hotline.

Image: Sewer/Water Rehabilitation near 500 E/500 N | 08/06/2024

Image: Sewer Rehabilitation @ 100 E/100 S | 03/05/2024